PROJECT OVERVIEW
■ ■ ■
ALS International was engaged by Alinta Energy to deliver the complete installation of a battery energy storage system (BESS) at the a regional project facility in Western Australia.
The project involved the transportation, heavy lifting and precise placement of battery modules, transformers and associated infrastructure, all completed safely and on schedule.
PROJECT DETAILS
■ ■ ■
Client: Alinta Energy
Location: Wagerup, Western Australia
Sector: Renewable Energy
Services: BESS Installation, Heavy Lifting, Transport, Engineering
Project Start: 15/12/2024 – Project End: 20/07/2025
SCOPE OF WORKS
■ ■ ■
ITEMS INSTALLED
■ ■ ■
128 x 20FT Batteries
16 x 40ft PCS 26t each
1 x Switchroom (90t)
1 x LV Room (26t)
1 x 133t Transformer
EQUIPMENT USED
■ ■ ■
Stradler
Gantry
Various Cranes
SPMT
Transport to Site – Managed logistics and heavy haulage of containers, Transformers, LV rooms etc.
Battery Installation – Coordinated the placement and installation of 128 x 20FT battery units and 16 x 40ft PCS units using specialised equipment including straddle carriers and gantry systems.
Heavy Lifting – Executed precision lifts for the 90t switchroom, 26t LV room and 133t transformer using cranes and SPMT.
The project was delivered with zero safety incidents and within the client’s schedule requirements.
PROJECT GALLERY
■ ■ ■
MORE PROJECTS
■ ■ ■
Pluto 2 LNG Compressor
Compressor installation for Woodside Pluto 2 LNG project. Heavy lift operations using climbing jack-up system technology.
Orora Beverage
Complex alternative lifting and installation project. Multi-phase equipment relocation using hydraulic jacking and skidding systems.